Shed 3 Construction Updates

Welcome to the Shed 3 Construction Blog!  Check back often to monitor the construction progress and make sure to visit the Construction Image Gallery.

The complete renovation of Shed 3 began on January 5, 2009.  The Shed, built in 1923, will receive a complete renovation including new concrete flooring with radiant heat, all new electrical, the addition of public restrooms, restoration of the original windows and more! 

The project architect is Kraemer Design Group and the construction is being managed by a joint venture between KEO Construction and Turner Construction.

Construction is expected to take 10 months with final completion scheduled for October 2009.  The Shed will be completely closed January-Mid April, when it will reopen for Saturday use only.  Construction will continue during the week.

Shed Construction Blog

Shed 3 Construction Update

Posted on August 27, 2009 - 1:39 pm

Thursday, August 27, 2009


The first garage door went in today!  They look great.  Top windows should be wrapped up by early next week and the big windows will go in soon.

...

Read More. | Be the first to leave a comment.

Shed 3 Construction Update

Posted on August 18, 2009 - 4:04 pm

Tuesday, August 18, 2009

The first set of pedestrian doors were set today on the north wing of the shed.  Installation of the garage doors will start tomorrow.

...

Read More. | Be the first to leave a comment.

Shed 3 Construction Update

Posted on August 1, 2009 - 8:44 am

Saturday, August 1 2009

Windows started going in!  The first windows were installed on the upper clerstory this week.   Also, the bathrooms are almost complete, the electrical conduit rough-in continues and the painting has begun.  For an idea of what the shed will look like when complete, check out the east wing.

...

Read More. | Read the 1 comment on this artilce.