Shed 3 Construction Updates
Welcome to the Shed 3 Construction Blog! Check back often to monitor the construction progress and make sure to visit the Construction Image Gallery.
The complete renovation of Shed 3 began on January 5, 2009. The Shed, built in 1923, will receive a complete renovation including new concrete flooring with radiant heat, all new electrical, the addition of public restrooms, restoration of the original windows and more!
The project architect is Kraemer Design Group and the construction is being managed by a joint venture between KEO Construction and Turner Construction.
Construction is expected to take 10 months with final completion scheduled for October 2009. The Shed will be completely closed January-Mid April, when it will reopen for Saturday use only. Construction will continue during the week.
Shed Construction Blog
Shed 3 Construction Update
Posted on March 21, 2009 - 3:10 pm
March 21, 2009
All the major radiant heating pipes are in and the final grading work has begun.
...Read More. | Be the first to leave a comment.
Shed 3 Construction Update
Posted on March 18, 2009 - 2:30 am
March 17, 2009
Radiant Heat prep continues. Stone for concrete floor base will be placed this week. Restoration of the brick work has begun.
...Read More. | Be the first to leave a comment.
Shed 3 Construction Update
Posted on March 4, 2009 - 10:35 pm
March 4, 2009
Trenching is well underway and the placement of the radiant heat pipes has begun.
...