Shed 3 Construction Updates
Welcome to the Shed 3 Construction Blog! Check back often to monitor the construction progress and make sure to visit the Construction Image Gallery.
The complete renovation of Shed 3 began on January 5, 2009. The Shed, built in 1923, will receive a complete renovation including new concrete flooring with radiant heat, all new electrical, the addition of public restrooms, restoration of the original windows and more!
The project architect is Kraemer Design Group and the construction is being managed by a joint venture between KEO Construction and Turner Construction.
Construction is expected to take 10 months with final completion scheduled for October 2009. The Shed will be completely closed January-Mid April, when it will reopen for Saturday use only. Construction will continue during the week.
Shed Construction Blog
Shed 3 Construction Update
Posted on June 30, 2009 - 11:06 am
Tuesday, June 30, 2009
The letters for the roof sign arrived today. If the weather cooperates the sign may be erected on Friday or Monday. The SHED 3 sign will look just like the SHED 2 sign and will help visitors know what shed they are in.
...Read More. | Be the first to leave a comment.
Shed 3 Construction Update
Posted on June 8, 2009 - 8:54 am
June 7, 2009
Demolition continues on the upper windows and the roof. With the old plastic removed, the Shed is much brighter and seems more open. It will be great when there are real glass windows in their place.
...